Ocean City Dredging Progress Reclaims North-End Beaches Ahead of Labor Day

Get the latest on Ocean City’s $19.5M beach replenishment project, active pumping locations, and open beach access points for 2026.

Great Lakes Dredge & Dock Company has advanced continuous sand-pumping operations near North Street as part of the $19.5 million north-end beach replenishment project commissioned by the U.S. Army Corps of Engineers. The restoration work is delivering roughly 1.6 million cubic yards of dredged slurry to reconstruct severely eroded shorelines extending from the terminal groin near Seaview Road down to 12th Street. Pumping runs 24 hours per day, creating rolling beach closures of roughly 1,000 feet surrounding active discharge locations to maintain public safety.

Dredging along the downtown stretch from 1st Street to 11th Street is now complete, successfully establishing wider beach profiles, elevated protective berms, and emergency sand stockpiles. Submerged delivery pipelines along finished southern sections are dismantled exclusively during night hours to avoid disrupting daytime visitors. Work is now focused on directing sand slurry northward toward Great Egg Harbor Inlet to finish the 11th renourishment cycle under Ocean City's 50-year federal coastal protection agreement.

Maintaining Access and Public Safety During Renourishment

To keep the shoreline accessible, temporary sand access ramps are constructed over overland delivery pipes at open beach access points. Municipal authorities issue daily beach opening maps, ensuring beaches north of Morningside Road and south of North Street remain open under active lifeguard supervision.

“On the barrier islands, location drives everything. The right street can make all the difference,” said Mike Sutley, Team Leader at Lexy Realty Group.

Beach renourishment projects remain a critical component of coastal living, protecting infrastructure and public recreational spaces. Homeowners and buyers interested in tracking municipal improvements across barrier island communities can review broader real estate trends and updates at Lexy Realty Group.

Key Project Features and Timeline

  • Project Investment: $19.5 million USACE contract executed by Great Lakes Dredge & Dock Company.

  • Total Volume: 1.6 million cubic yards of sand distributed along the north end.

  • Completed Sector: 1st Street to 11th Street fully restored with elevated berms.

  • Active Area: Pumping currently active near North Street, moving toward Great Egg Harbor Inlet.

  • Operational Schedule: Continuous 24-hour pumping with 1,000-foot active safety zones.

Frequently Asked Questions

Which Ocean City beaches are currently open?

Beaches north of Morningside Road and south of North Street are open under lifeguard supervision, alongside completed sections from 1st to 11th Street.

How do beachgoers cross the delivery pipelines?

Engineers construct temporary sand ramps over overland pipes at open beach entrances to allow safe public access.

Why is pipeline work completed at night?

Submerged delivery pipelines are dismantled exclusively at night to minimize daytime beach closures and reduce disruption for visitors.

Sources: City of Ocean City; U.S. Army Corps of Engineers